Intermodal Pedestrian Overcrossing Update

The new elevator which provides access to the Pedestrian Bridge on the north side of the railroad tracks is now installed. While the elevator is complete, the plans call for the exterior of the elevator tower to be wrapped with glass. In
December of 2019, the general contractor for the project, Gordon N. Ball, learned that their subcontractor working on the projects had not ordered the exterior glass for the tower. Gordon N. Ball immediately ordered the necessary materials, however the manufacturing of this glass, even through an expedited process, requires a 12-week lead time. The new completion date for the project is now April 2020.