Golden Hills Park Improvement Update

Unfortunately, it was necessary to terminate the contract with the original general contractor and the project is being rebid.  The following reflects the new project schedule:

September 4, 2019           Authorize rebid

October 3, 2019                Receive bids

October 23, 2019              Award contract

November 4, 2019            Preconstruction meeting

November 11, 2019          Begin work on site

June 1, 2020                     Complete construction

The construction schedule includes a month for anticipated rain delays.  The contract with the vendor who will provide the new building has been executed and the modular building materials have been ordered.  The contract with the tennis court installer has also been issued. The general contractor will be able to construct the building pad and assemble the modular building once the materials are delivered to the site.  The tennis court resurfacing and turf restoration work will require warm weather. This work will be scheduled for early spring 2020.

Top