Pavement Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The City’s street improvement program, funded by Measure D, selects and schedules street repairs each year. The community is divided into five zones, and paving work cycles through them on a five‑year rolling schedule so every area receives regular maintenance.

2026 Summer Paving Project

2026 Paving Projects Current Expected Work MapThe City’s next paving project is scheduled to begin in summer 2026. Major streets included in this phase are:

  • Alhambra Avenue (Bertola to Highway 4)
  • Alhambra Way (from Alhambra Avenue south to Muir Station Road)
  • Pine Street (Bush Street to Highway 4)
  • Shell Avenue (D Street to Pine Street)
  • plus several residential streets

This project will rehabilitate and resurface pavement throughout the area. Work will include crack sealing, base repairs, adjustments to surface‑level utility structures, construction of ADA‑compliant curb ramps, and new pavement striping.

Full list of streets included in the 2026 Paving Project

Planning for 2027 Paving

Paving that will be done in summer of 2027 will focus on Zone 5 of our Paving Progam. 

As part of the planning process, the City held its annual Measure D public workshop with the Council’s Franchise/Public Infrastructure Subcommittee on the evening of January 14, 2026. City staff presented the Fiscal Year 2026-27 Measure D Five-Year Pavement Preservation Program plans:

For more information and to view past Measure D documents by year, please visit the Measure D information page.

Map of Paving Zones, by Year
Types of Road Repairs
Pavement Management Program Update (PTAP)
Past Paving Projects